Speakers labeled via automated voice-based diarization + AI name-matching against the city's official roster. Automated transcription can still mis-hear a name during fast speech (e.g. a rapid roll-call vote) -- clear near-misses are auto-corrected, but this is not manually verified line-by-line. Treat names as a strong best guess, not an official record. Home addresses that residents give are left out of this page.
[0:33] Mark Waltz: Good evening everyone. Thank you for coming to our meeting tonight about the Tedford Road reconstruction and the sidewalk. I'm Mark Waltz, the town manager, and we'll go around, do some introductions here, and then I'll kind of set the stage before we turn it over to our engineers.
[0:47] Josh Jennison: Chief Mark Hagan, chief of police. Matt Hunter, public works director.
[0:52] Chris McDonald: Chris McDonald's, civil engineer with BH2M. Steve Blake, also a civil engineer with BH2M.
[0:57] Mark Waltz: Josh Jennison, deputy director of public works. So many of you were here probably two years ago when we had a draft planned to basically help us choose which side of the road we wanted the sidewalk on, and the consensus of the group that night was that the preferred side was the West side of the road. For those of you that weren't here, this project has been requested by your neighborhood for a long time. People have said it'd be much safer to walk on the road, they'd like to have a sidewalk there. Our former public works director initially was hoping it would be a much easier project. You may have noticed a few years back we added sidewalks to Thompson Fair Top, some Fair Thompson ball tops up your mall road down by Best Buy, and for that one all we basically had to do was pave a part of the shoulder. But it quickly became apparent once the engineers got involved in Tedford Road that because of the road is so flat, if we just paved the sidewalk in, what we'd do is create all kinds of drainage issues. And then as most of you know, your road is about 200 years old and was originally for horses and then just kind of got paved over and was never properly built. So to do this project we end up having to rebuild the road, which is good because we'll have a you know good quality road, but it certainly increased the cost a lot. We went from a project that we thought would be roughly 200,000 to one that's gonna be about two million to rebuild the road, put the drainage in, put the sidewalks. The first piece of this was done a couple years ago when we had to redo the culvert at the end of the road. We thought since we're digging it up we may as well put the sidewalk walk in there. So that piece already has it in, but now we're looking for the rest of it. The select board approved an RFP earlier this year for the design work to follow on from the preliminary choice that you folks have made of which side of the street, and BH2M engineering firm won that. They've been out a number of times viewing the road with town staff. staff they're actually going to be out once more next week with a survey group just to verify the locations that are in the prior survey and see what may have changed and now that they know pretty much what they think they want to do with the design they want to again verify points figure out with drainage is going to be stuff like that we had a question earlier which I'll address now and then we'll certainly take more questions and comments in a few minutes after they open up with their presentation. The question earlier was when would you hope to do this. The hope would be we would try to do this next summer. So the steps that are remain to be involved is they would finish their design. The water district has joined in this project because they need to replace your water line that goes down Tedford Road, so they are going to be paying any costs associated with that portion of it, and there should be a little, at least a little bit of overlap of things that are mutually beneficial so it should be a little cheaper for both the town and the water district to do the project at once. So what would happen is they finish their design, then get approval for the select board to put things out to bid. We would then get actual numbers back rather than estimates. Heard a little bit that maybe some of the contractors are getting a little hungrier for work next summer, so hopefully that might mean little more favorable prices than we would have gotten otherwise. And then we have that we could access in our kitty through various things, somewhere around a million right now. And then there'll probably be roughly final numbers based on what the bids come back, be another million that we need to go in the capital improvements for next year's budget that would make it through the budget process. All this is subject to approval at town meeting. So we won't be able to say absolutely certain it's happening next summer until the end of the budget process including town meeting, but that's the plan right now is to try to make that happen. Because as I know some of you have been frustrated, this is dragging on forever. We'd like to get it done too, so that's certainly our goal is to try to find a way to make that happen. With that said, I'll turn it over to our engineers and then we'll take comments and questions after that.
[5:18] Chris McDonald: Okay, well, again, thanks everybody for coming by. My name is Chris McDonald from BH2M, one of the design engineers on this project. So Tedford Road, the existing conditions on this road show about a 20 to 22 foot wide road with no shoulders on either side, and the road length is about 4,000 linear feet. What we are proposing to do is to design and construct a sidewalk along the western side of the road, and in the plan that Steve has up here you can kind of see the very beginning of it anyway. When we say west side of the road, as we're looking up the road that would be on the left side as we're, as we're going from Middlesex up. So the project looks to put sidewalk along that entire west side. That'll include going across the railroad tracks and then up to meet the existing Culver crossing that, as Mike said, was constructed a couple years back. So basically the sidewalk would meet that existing sidewalk. As far as the drainage aspects of the project, given that we're going, given that we're going to be putting in a sidewalk on the western side, one of the things that happens with the curb line is that the runoff kind of hits the curb, so we need somewhere for that water to go. And so what we're looking at doing is strategically putting catch basins in along the sidewalk side to be able to capture that water and then drain that water away from the road. On the opposite side of the road from the sidewalk, we are proposing to put in about a two-foot-wide gravel shoulder, and again, that's just to make sure that there's appropriate width for the road. On the water main side of the project, the project is currently proposing to extend the existing water main. The existing water main goes to, I forget the name of the road, the existing water main goes to about, you know, I think it's like somewhere around three or four hundred feet from where the stream crossing is today. And so effectively what will happen is that the water main will be extended to provide service all the way to the end of Tedford Road, to the other side. Thank you, just pass someone and so the proposed water line will extend water all the way to the end, as far as what you may see on the surface for that. The other thing that the project is proposing to do is replace all of the fire hydrants that exist along Tedford Road, as well as adding some additional fire hydrants in that area of main extension. And I guess the biggest note of the fire hydrants is that our current proposed alignment with those has the fire hydrants behind the proposed sidewalk. So basically what we'll be doing is taking the fire hydrants and putting them on the opposite side of the road where they exist today. And I think that's the meat of the project. A couple of quick notes on this. The right-of-way on Tedford Road today is relatively narrow. It's a two-rod road, so it's about 33 feet wide. And we were proposing to put in two-foot shoulder, two 11-foot lanes, and a five-foot sidewalk that takes up a lot of the right-of-way. So as the road gets, one of the reasons why the road needs to be reconstructed is so that we can center the sidewalk and the road within the right of way. If we just simply kept the road in exactly the same place it is, the sidewalk would go over the right of way. So in some ways we're kind of realigning the road a little bit. And the other thing, as far as proposed conditions, we discussed drainage a little bit. One of the things that we're looking at is trying to add a little bit more grade to the road and areas so that we can get positive drainage along the curb lines so that again, the road will drain properly. And I know in existing conditions today, there's a lot, especially on the Middlesex side, there's a lot of flat areas. So what that's leading to is some of the divots and depressions you see in the road. And then I believe there was some pavement work that's been done over the past couple of years as well, where that pavement breaks up. One of the big reasons why that happens is water's just sitting. So as part of this project, we look to try to improve the drainage along Tedford Road to try to give that a more lasting sub base and part of that drainage work includes an underground storm
[9:49] Steve Blake: break system so along that proposed curb line we would have catch basins and an underground storm grain just we'll have it in along most of the stretch of road it's not quite 4 000 feet but it's probably three quarters of the word we would have that and just through the nature of adding a curb to an existing road we have to include something to drain that along the curb line as well so there are we have plans up on the screen we have a hard copy a full-size hard copy of the drought plans here and then we also have a larger scale blow up of the entire corridor that we're looking at each one of these plans ends has some has a few different colors on it that we just wanted to highlight so anything blue would be waterline anything green would be the proposed storm drained and then anything red is what we're looking at for the proposed limit of work for construction a
[10:55] Mark Waltz: couple of the things that may be of note is they've had some discussions with the post office because some mailboxes need to be moved and the post office is asking that all the all the mailboxes be moved to the east side of the road so they'd be on the opposite side of the road of the sidewalk and another interesting thing of note is the railroad crossing we were anticipating or hoping that we wouldn't have to rebuild it at the end and save that money because of the fact that the state has approved the railroad there to become a trail until rail however when we reached out to the state the portion of d.o.t that deals with the railroad tracks they were not at all in favor of not replacing the railroad tracks they said they've got someone that's proposing to lease the railroad tracks and it appears that the lease is basically not to really go anywhere but the tracks in brunswick that go up along route one have been leased to a company that has real service to rockland And they don't have enough place to store their cars that aren't being used. So you may have noticed when you take Route 1 through Brunswick, now over the highway, you see some cars in storage. The state's being asked to lease this part of the railroad track to store some of their cars. So because they haven't made a decision yet, and I've asked whether that's considered important enough just to use it as storage, that it could defeat the trail, they said, well, that's a good question, and they're still thinking about it. But they said we have an obligation under federal law that there's any possible chance it could still be used for rail, that we can't allow the tracks to be taken up yet. The good news is that they've offered to pay for the railroad rebuild, so the town wouldn't have To pay for that part, so I guess that shows how committed they are, they want to keep the tracks there. So what would happen is the tracks would get pulled up as part of the project, and then the state would hire a crew that would put the tracks back together. The most, probably the biggest inconvenience for anyone that lives north of the river tracks, is that'd be about a two-day period when you wouldn't be able to cross the railroad tracks. So what we would do for that is similar to what we did when we had to build the culvert and the people north of the culvert couldn't get there, is would approach the owner of the Highlands and asked if we could temporarily use Audubon Way for two days so people could get in and out of that end. In the past we traded the use of Audubon Way for the grading of it, and he was more than happy to do it. So that's what we'd work on so that people could still get back and forth to the houses and we could get fire trucks and whatever else. But we were happy to know at least we wouldn't have to pay for the rebuild of the railroad tracks, so that will save us a little money there. So what we'd like to do is take any questions generally about this or comments. As we were walking down the street, we had some people approach us and they seem quite anxious to have this happen, and but if you don't want this to happen or if you do want it to happen, feel free to step up to the mic, just say your name and address, make a comment, and then once we've taken any comments in general, we'll let the group kind of devolve into looking at the maps and these guys can answer specific questions you may ask, is my tree going to be affected, or maybe you watch your tree affected on so that it would get taken down. So feel free to ask questions, things like that, whether regarding trees, mailboxes, like we probably answered the mailbox part already, but and these guys can address your questions and we're happy to discuss more. So if anyone would like to make a, ask a general question or a comment, go from this stuff up to the microphone.
[14:30] Public commenter: Problem, all the water once you get past the rail tracks comes to the back side of my property and comes across drainage system there that I don't know who did it, but the water comes from all that water in there. How are you going to address, because we have a dish that runs the
[14:55] Mark Waltz: whole length of our property. Can you give your name and address just so these guys can identify?
[15:00] Public commenter: If I've got [address] and your name is we got we got that we got that because it comes and then it turns and it goes right down the road it comes off all the water from out back there comes right through our property yeah I once you put a sidewalk there we're going to lose that ditch and I'm assuming you're going to put a bulkhead cash basin in on my property good yeah I'm familiar
[15:24] Chris McDonald: with which property that is it's like a masonry building and there's the ditch line that comes down then follows the road there's a culvert that goes across all the water from out back yep down from there yeah it sure does so yeah we've actually been looking at that area pretty intently trying to try to work that out and what we're proposing right now is that where your swale comes down and then makes that 90. Yeah so where it makes that 90 degree now what we'll propose to do is put a basically like a culvert inlet at that point and then we'll have the ditch line that goes across along the road there because to your point the sidewalk is basically going to kind of come into that so rather than trying to regrade a swale and everything else what we're going to do is try to take advantage of the low point put a catch base in there with maybe like a domed top on it or something like that similar to what you see on the on the southern side of the railroad tracks on the flatter areas there's some there's some yacht drains so we would basically do something similar to that would then tie into the closed drainage system that closed drainage system will then proceed down to the culver crossing and empty out into that pond area sir
[16:34] Public commenter: larry weathers 87 tempera there's a lot of large pine trees right next to that property and all along the ground have you had an arboret come out or anybody make sure when you would jump the road you're not going to deteriorate are you going make sure you have somebody double check you're not going to deteriorate the trees to the point where they could fall on our houses and neighbors houses anything like that
[17:09] Chris McDonald: To explicitly answer your question, no, we have not had an arborist come out and do that, and we haven't had a chance to assess each individual tree. I think the, I guess in consideration restoration of that, the trees that are very close to the road we're going to be looking at a full box cut is what we would, what we would call it, which is basically that we're going to have to go through because as Mike mentioned the road is kind of an older road which never really had an appropriate sub base. One of the parts of the reconstruction of this road is that we'd have to dig down, you know, two to three feet and box cut out that existing area, put back in appropriate materials to rebuild the road back up. So the impacts that we're talking about along most of the road are relatively shallow in comparison to tree groups. So I think that some of the larger trees that are farther back from the road should not be affected. I think the bigger question is the road, the trees that are directly on the road now where we're going to be widening the road, those are the ones that are probably going to be affected, and those are the ones that they would look to probably take down during the construction of it. I live across the street at
[18:25] Public commenter: [address] and they have a large pine right on their side of the road at 87. If the, if the root system disturbed, my tree roots only the tap root grows deep, the rest of it is shallow. So when you disturb the root system of that tree it can reach my house and it can reach my child's bedroom, so that's a major concern of mine. I don't want to have to spend every night wondering a tree's gonna crash on my children's bedroom. I know I'm in favor of the project, I just want to make sure that the safety of my house is addressed. I'd say use tonight once we kind
[19:01] Mark Waltz: of break up to the call these guys attention the particular trees, like for instance there's one in front of Mr. Muzzy's that when we were out walking the road there's a large one there that, but they said you know probably better to be gone, and we talked to Mr. Muzzy and he said yeah it'll be fine with me if it came. So if you've got trees that you're particularly concerned about that are near the road, call it to their attention, we can figure out how to dress Andy
[19:30] Steve Blake: Rule 43 Tedford, does any part of this plan involved, I thought in the past when they talked about this there was plans to like open the other end of the road up, is that ever a plan to like alleviate some of this traffic
[19:42] Mark Waltz: From so the owners of the Highland have come into our planning board multiple times to get the plan approved for a memory care facility that would be on Audubon. They have said at different points that if they when they build that they would build the road similar to what they did with what they used to call Mountain Road that's now the public portion of can-am. So you'd have a multimodal path on one side and you'd have the street and the other. Then they've said at that point, they would like to propose to turn it over to the town to become a town road. The town had the traffic study done mid 2000s that said it would like to have another way to get traffic than going through the four corners at 196 and 201. So kind of the vision we've been working on in pieces is to eventually have a connection that goes from the schools the buses are already using even though it's not public road yet but come up can am the part that's private and then get to the cannon part that's public out to Village Drive Village Drive is now public and then eventually have Autocon become public and connect to Tedford so that's kind of the long range but there's a couple pieces that need to happen before that one is the Canadian piece needs to become built appropriately to be a town down road and then be accepted and then the second piece would be the Audubon one let's say the K&M would probably happen before the autumn Audubon one so long-term plan but yeah nothing in the immediate future discussion thank you I see Jenny Little who's the president of the tops of Trail Riders here can you guys talk a minute about the ideas that we've got for dealing with where the ATV Trail in the area of the river tracks you want to show that section I have a
[21:36] Public commenter: question on lease the lease yeah the lease that they're gonna who are these people coming in and gonna store cars up there by the tetra on the railroad track it's the whoever the company is
[21:49] Mark Waltz: that's leasing the rockland to brunswick piece of the railroad tracks okay they're currently storing cars on the piece of the railroad tracks that is basically between route one and what they used to call hobo junction right now they're currently storing there but they've asked for at least so they could back cars further up basically to come as far as the cadence road sidings well that's
[22:13] Public commenter: it's funny you use that word hobo because i'm thinking of storage cars and we've got a lot of people walking up down tedford road now and now we're going to have that connection going up into the highlands the concern of mine would be who's who's going to monitor this are they going be a lot is it going to be hazardous material in them what could what 's the rules this company can they sell anything they want in new spanish you know i think they're empty cars
[22:41] Mark Waltz: But at this point the state hasn't granted them the lease so I don't really know any details on that part I mean to be honest and Brian Banton has heard from me before my hope was we could actually take the trestle down that's on Elm Street because we've got an 18-inch sidewalk walk on Elm Street and no bike lane. So what we would do is working on pieces of a master plan. It would be nice to be able to take down the trestle at Elm Street, and then if Thompson were to be involved in the first section of this trail over the railroad tracks, would go from Elm Street to Tedford Road. And you'd go in a decline from Tedford Road to Elm Street so that you could bring the pedestrian and bike traffic or the trail traffic. Down to Elm Street level so then people could get on to the Andrew Scoggin River bike path and cross over the Merrimet bridge but the state right now is reluctant to listen to me too much because they've said as long as they've got a trestle that still could hold a train they don't want to have it removed so but you know things may change they haven't made any final decisions that's what I'm lobbying for is to try to get permission that we could get rid of that trestle but as of yet this Because of this proposed lease the state hasn't been to the point that they want
[24:02] Public commenter: To say we don't want we'll let you take the tracks up well no that the state doesn't run down there either but I'm just saying you know that I'd rather keep it on the public side don't know if this company is going to bring those railroad cars and
[24:19] Mark Waltz: Topsum is not asking to have railroad cars
[24:24] Public commenter: And the state has given the license and we won't wait it.
[24:28] Mark Waltz: We don't okay it. We have no role in that. It's the state. Yeah, exactly. I'm asking to them to consider letting us at first was just not to put the tracks back in crossing Tedford Road. And then the next piece would be for them to consider letting us take down the trestle and build that as the first piece of the rail trail. And how long would that at least be for lifetime? Or I doubt it again, it's not with us, it's with the state, but usually there's a period of years, and usually the railroad eventually goes bankrupt, and then you know at least the Bruntwick to Rockland Railroad seemed to go bankrupt.
[25:04] Public commenter: They only last a few years, and then yeah, it seems like we got some questions on that.
[25:09] Mark Waltz: The cement plant is closing, and it looks like I think the cars that I see at least over the railroad tracks, the ones that would carry cement stuff, so if this once the cement plant is done, that may negate some of that desire anyway, but we have we have no ability to approve the lease, we're actually again trying not to get the lease there but trying not to let that happen, right, okay, because I would like to see the truss will go away so that we could make Elm Street better and then have a nice. Bike pedestrian connection from Elm Street to Tedford Road.
[25:47] Public commenter: Man, hi, are you done? One more comment on that, it was my interpretation also that the actual car storage was going to be further up from like Madeleine Drive to Cat Inch Road where it's a double set of tracks, I wouldn't foresee them storing anything on the line because they'd keep going for maintenance, that was my interpretation, yeah, it's a it's it you. Know it certainly opens up a big path for anybody, I don't know what the least looks like or what. It's going to say, but we don't either, you know, it's but there is a double set of little known double set of tracks, yeah, a little bit further up, so we're talking headed out, we headed towards. Or Cat Intro, yeah, the answer Jim Howard, and given where across the world. Yeah, it actually is, it's funny, it goes past Cat Ants, but on Cat Intro the double set is down to single, yeah, so it's like double single double, well I like your idea Mr. Manager, that's not.
[26:58] Mary Beth (Bike Path Committee): Hi, this is Mary Beth from the Bike Path Committee, and as long as you're talking about bike paths, wouldn't it make sense to try and put bike lanes on this road?
[27:13] Chris McDonald: Yeah, it would be great to be able to include that if we could, unfortunately, the width of the right-of-way just won't allow it,, we have the right-of-way that goes along Tedford Road right now is defined as a two-rod road, which is effectively 33 feet wide, and so when you have the two 11-foot travel lanes and then the five-foot sidewalk, that effectively takes up most of the right-of-way as it is. So unfortunately for Tedford Road, it's not a great fit only because there just isn't the real estate there to support that many lanes going across and behind. Your question is the sidewalk. Is there any space between the road and the sidewalk? And again, just given the width of the road, it's going to basically be a curb and sidewalk, so there won't be, there won't be room for an esplanade in between the sidewalk and the and the driveway. Most roads are three or three rods wide or
[28:12] Steve Blake: or 50 feet, so this is a little bit unique or it's a very old road. It's it's it's very narrow, you know, it's it's 17 feet narrower than a typical road, so we just we don't have room to do anything within that right away beyond reconstructing the road and building a new sidewalk block.
[28:33] Paul James: Hello, my name is Paul James and I live in 16 Tiffin Road. Myself and the neighbor on either side of me is willing to give up land in order to have a green strip. But the lady was looking that ass long. Is that possible?
[28:52] Mark Waltz: If you wanted to give up? Well, let me qualify that. You probably couldn't give it up as long as you even you have enough setback, you know, moving the property line, but it doesn't do us too much good just to have two houses that want to, we need three, but I know there's still a small number, so yes, it is certainly possible to give the town land or an easement to go on your land if you wanted, but unless we could do that for a big chunk of the road would doesn't really help us widen the road. The other problem we've got is where the CMP poles are, the sidewalk's going to be basically right up against the CMP poles and we don't want to have to move poles because we'll add hundreds of thousands of dollars to the project, so we're trying to use the poles where they are. Okay, thank you.
[29:43] Public commenter: With the back center signing off to the polls, yeah.
[29:47] Glenn Thurston: Yeah, Glenn Thurston, a little bit, nine ten foot row. I was wondering how you anticipate the row looking when you're done, because you're talking drains on the west side and I know now when I wash my wash a vehicle in my yard the water runs to the road and clear the corn, so is the grove elevation going to be pitched to the west and lower, or is it going to be, how is it going to take care of in the winter it freezes from my house to the corn? Yeah, and Steve.
[30:26] Chris McDonald: If you could bring up the profile on that beginning. Yeah, so yeah, we've taken a look at the of the running slope of the road if you will, so the grain that runs you know along it, and that first section of Tedford Road is very flat. Typically you know typically you'd like to see well I won't throw numbers out there, but given how flat it is that's one of the that's one of the issues leading to some of the drainage concerns or the drainage problems that you're seeing out there today. So one of the things that we're trying to do with this road reconstruction is to add some pitch to the road. Now of course we can't add a ton because we just start to raise the road up you know those impacts start to go off, so we're trying to balance you know keeping the road within the right of way and keeping the impacts to a minimum but still provide enough pitch in the road to be able to drain, so in that beginning section we're looking at about a half percent which you know to be quite frank with you is still a pretty flat road but at least it gives it some improvement over how conditions are out there today. In your specific area the stormwater is still in the runoff is still going to run in the same direction and it'll still go to Middlesex to drain, but again adding some pitch to the road we expect there will be some improvement on letting that water run instead of having it slow down or not
[31:49] Glenn Thurston: even move because there was some talk about putting a catch basin or catch basins on that side to take care of that because we talked about tying into the end one but that was explained that 's the state road versus 10th road drainage right and to be frank with you it's
[32:14] Chris McDonald: a great it's a great comment and something that we can look into a little bit more to see if it's appropriate to put some catch basins on the non-sidewalk side, but again you know I for the non-sidewalk side, most of the drainage on that is gonna remain relatively close to how it is today. Again, what we're trying to do is we're trying to make sure that there's enough pitch in the road so that we can sheet it appropriately so that it won't stagnate on the road. So again, trying to minimize the icing conditions and that sort of thing.
[32:43] Glenn Thurston: Because that's the only thing, my driveway, even if it does drain to the other side of the road, it's gonna run across the road.
[32:50] Chris McDonald: Well, right, and we wouldn't do that either. We're proposing to have a, and that's kind of part of road reconstruction as well, is putting a crown back in the road. And there's some areas of the road that are just really flat and just kind of really beat up, you know. So that's one of the other things is trying to put a crown in the road going, you know, kind of across it so that the water will sheet off, and then putting pitch in the road so then the water will run. And so as part of reconstruction the curb lines or gutter lines will be better defined so that water will run away from the road and run along the edges instead of down the
[33:25] Paul James: middle. Yeah, I
[33:28] Glenn Thurston: know on the plans it says possible impact i have two pine trees and a chain link fence do you anticipate that 's going to be when i've cut those trees and i was asking you earlier if you'd move the fence back or what would happen yeah if the fence if the fence doesn't
[33:52] Chris McDonald: in fact need to be impacted, then the fence would get replaced or pushed back depending on what the configuration of the fence would be. On trees, again, we'll have to look at that on a, on a case by case basis. I'll say this off the top that the trees that are very close to the road, I think it would be in most people's best interest to have them taken down. If they're, if that's amenable, we could try to work around trees the best of our ability, but again discussing the box cut and the shallow roofs that were discussed as well, you know, there's a risk to keeping some of those larger trees. So the more trees that we could take down as part of this, I think the safer that the road will be, and you know, less problems will be in the future. Yeah, I had a question to add
[34:38] Public commenter: to that. We're 141 and 149 upon the games where you have that long run of trees at the end of the Tadford Road, so we have all those trees going to the culvert. You're on the forested side. Yes. So I know, I don't know how far you're going to go back, but do you foresee a lot of those trees having to come down because a lot of them are really close to the road. Yeah, I know, I know which
[35:06] Chris McDonald: section you're talking about. So that's really between the culvert crossing and kind of the first houses, so it's a really wooded area. I think that section will see some trees taken down. We don't anticipate going very far from the existing edge of road on that side where the, you know, where the, where the sidewalk isn't going. So you know, I would say one or maybe two trees back would be, would be about what we would expect. Okay, and the other thing we wanted to ask
[35:37] Public commenter: Ask is with you bringing the water up the road. Most of us, you know, we have wells. What is going to be the cost for us if we wanted to tap into the water? Yeah, so well on the west side you're gonna have you're gonna have the sidewalk there. You have to depend on if you don't tie in
[35:59] Steve Blake: and prior to the sidewalk. Yeah, and so some of this will have to be discussed with Brunswick and Thompson Water District. But I, what we had talked with TC about is that possibly we could we could we could we could work something out where the contractor that's doing the work puts in the services at a cost to the homeowner. The alternative to that would be while the work is going on, you know, before the surface pavement is down, each individual property owner that would like a service hires a contractor to tap into the main and bring a service into their into their property. So the idea with extending the main would be to, you know, for the people that live along that stretch, the ability to tie into public water, but it would be at those individuals costs, at least in terms of tapping in a service. We'll be able to use some kind of stipend on the tap fee. I can't speak for the water district, so I, those are things that we'll probably have to figure out later on, just in terms of how, you know, how that
[37:10] Public commenter: gets how that gets paid for, because we're getting charged for the water that we're not using for the past how long, so sewer too. Well, that's how they do it, 15 years, 20 years, and so we don't even use we don't have, when we don't have the service, we don't have the service. They put in the sewer and after they're ever trying and they don't want and they make us pay a minimum fee for the last time we're going over is he ever had one. So if you bought that, yes, we've all bought it, there's nothing think we've been able to do about it. We'll leave when you're five. Thank you. Oh, that's so scary, you know, because we've been paying for something that we haven't used forever. So you've been paying
[37:54] Mark Waltz: for water even though you can't get out. Yeah, well, it's just sort of the sewer line does go by
[38:00] Public commenter: there, so that makes sense. It's a repeat that we pay, but everybody else on the tent, you have a
[38:06] Josh Jennison: meter above, you have a meter. I don't have any water meters to get that, and we've been paying
[38:10] Public commenter: of we don't need, we only get just the silver mine, that's it, and but they charge us a flat fee
[38:17] Mark Waltz: because that's how, you know, that's that's part of the reason they joined in this project because
[38:20] Public commenter: They want to put a water line there. Exactly, they'd like to and run it up. Yeah, we'd like to tap into it, right? I don't want to pay three bucks and I've already paid three thousand bucks for
[38:31] Mark Waltz: something I haven't used. Well, the water district and the sewer district are two different entities. So if you've been paying, if the sewer line goes in front of your house, and you don't join in. Yes, I do believe you end up paying just because it goes by your house. Hopefully you haven't been paying a water fee yet in that area, because if there isn't a water line to tap it, you have to meet a water to get the sewer bill.
[38:54] Public commenter: Bill, that's what they mean. But I can tell you what we will do is I'll pass along to the water
[39:02] Mark Waltz: district engineer that there's people here tonight that are interested in knowing more about how the connection water would go, and maybe they'll do like a mailing or something, or we could put
[39:12] Public commenter: something on our website with the answers. I don't think anybody's against the water coming down there. It would just be nice, like we said, to get something for you, for you know, 15 years the money you've been paying, if another. Yeah, and again I'll have to leave that defer to the
[39:30] Mark Waltz: water district, because that's up to their policies, management, their laws, which I'm not actually up on
[39:34] Public commenter: things. Just one other quick question with moving the mailboxes to the other side is that, are you going to tell us where they're going to put them along that tree line, because there's going to be, you like, you know, there's a bunch of trees there. That is a brutal system, it's kind of brutal there to bring those mailboxes across. Are you going to state where they need to go, or are we just going to talk with our neighbors and figure it out? [Chris McDonald: That's it, that's] a great question. That's a wooded area though, there's, there's nothing out there as you know now on right 149, so yeah, at the end. And I read the same thing, I heard that you guys are gonna pay to have the mailboxes put in, just like the hybrids, the new hybrids. I heard you guys are going to take care of mailboxes, is that true? I don't know if we're making the mailbox be moved.
[40:30] Mark Waltz: It's likely we would make that be part of the project. You would? Okay, so, and sorry, go ahead.
[40:37] Steve Blake: Yeah, I guess I'm just going to answer your question and I think part of this, part of, part of the answer with the mailboxes is some of this will likely have to be done kind of during construction with the contractor working with you when we have to relocate those mailboxes and feel fit the best location for those, you know, both from a vegetation perspective but also safety perspective. So we'll, we'll have, we'll placeholders on the plans. The contractor would be responsible for relocating the mailboxes, but we'll probably just need to be a little bit cautious about that during construction and make sure they get put in the place that's that's safest for, you know, whomever needs to walk across the road to pick
[41:18] Public commenter: up their mail. I think the biggest thing is like on Aryan down there the vegetation as you saw was really super thick. Yeah, you're going to have to remove a lot of vegetation to put a mailbox
[41:29] Steve Blake: box possibly. So yeah, sure. And these will still be close to the road. I mean, the idea is that, you know, that we have a shoulder on that side and they're going to want to, they're going to want to pull up and be able to put the mail in, so we're not going to be sending these back really far. They'll still be pretty close to the road, so I, you know, we would, we would avoid as much vegetation disturbance as possible with, you know, where we're locating the mailboxes. When we were
[41:54] Mark Waltz: walking the street last week we got nervous, so now we're going to move a cemetery because there was, there was a house just before that wooden stretch that had a cemetery by their mailbox, but good news is it wasn't real, so we don't have to look at that. It's just a decoration.
[42:07] Public commenter: I think that's there. He put it there. Yeah, we're worried about that too. We have to move all that stuff back that we have there, but I think it's far enough back, but we can talk about. Yeah, as they said, on that side of the
[42:24] Mark Waltz: road it's pretty much the back of the pavement. It's, we're not going much past that where it
[42:28] Public commenter: currently exists. We have a question. Where do you guys, where's the outlet of the story?
[42:37] Chris McDonald: That's a great question. Yeah, there's there's a few. So for the beginning of Tedford Road again, the flat area kind of you know south of the railroad tracks, there's already existing catch basins that are along the road. And so for the majority of those, the intent is that we're going to be using the existing drain outlets for those. So really what we would do is that we'd have to replace the basins themselves just to align them better with where the proposed curbs will be, but the outlets for those will all be the same. For the area north of the railroad tracks, we are looking at proposing a new outfall that's basically going to be in the same area as the rip riprap for the cross. The riprap is the stone that lines the that new crossing. And so what we would look to do is to bring the storm water from the about from where the railroad tracks are, bring that north, and then outlet it out the bank that way. So are you going to have some provision
[43:36] Public commenter: to make sure that water doesn't contaminate the farm water cross on mail armor? That's what's going to end up because it's going to go right down through our farm and that water is used.
[43:51] Chris McDonald: We are not proposing any treatment for the storm water as part of this project
[43:55] Public commenter: to make sure it's not contaminated. Right robes all kind of those people throw trash everywhere. Yeah, what is the lower line? You can just run a strong brain anywhere you want, just dump it.
[44:09] Chris McDonald: Is that what you're saying? But for municipal projects, treatment is not required.
[44:15] Mark Waltz: Right out of that. Yep, I mean the water's probably up in that same stream now anyway. It's just it will be more organized how it gets there. Well,
[44:25] Public commenter: they used to be a beautiful lawn there. Yeah.
[44:27] Steve Blake: I mean the structures that we'll build, they'll have they'll have some them that are that are designed to you know take a lot of large debris like a sediment grease. Exactly. Yeah, so it's there is some level of treatment just through the nature of how the underground structures are designed. They
[44:50] Mark Waltz: actually had designs when they did the culvert. They intentionally designed that to drain the pond because we were damaging people's wells because when we get a big storm event, not enough water could get underneath the road. So the intention they wanted with the more frequent rains and higher rain amounts and stuff, they wanted to make sure they could get the water down the stream. So that was intentionally drained point wasn't an accident that the pond went away. Okay, can you take a minute talking about
[45:24] Chris McDonald: What the ideas for the ATV trail? Oh yes, so the at the railroad crossing there's a there's an ATV trail that kind of comes down on one side of the railroad tracks, crosses the railroad tracks, runs along the shoulder line, and then goes across down the power lines. So as part of this design we are incorporating a what's called a tip down, which is basically just like when you have a sidewalk that comes to a driveway or to a road, the sidewalk tips down and then kind of runs it great along the road so. What we're proposing is that effectively opposite where the trail goes up the along the power lines, we're going to have an eight foot wide area that will allow for at-grade crossings there. So the snowmobiles, ATVs won't have to ride up the curb to get to the back of the sidewalk. There'll be a depressed area where they can cross there, then they can ride along the edge of the sidewalk and then rejoin up with the existing trail.
[46:24] Mark Waltz: So currently the trail they kind of they come in drive go along the side of the road and then get this way. So the thought is the sidewalk is going to end, it has to be at least 12 feet from the railroad tracks under the for the railroad rules, and then things will be at grave until you get 12 feet after the sidewalk will start again. The ATVs will be on the back of the sidewalk until there's a place they can cross perpendicular to the trail, and we've already started talking to CMP and it looks. Like they will be fine with that, so it keeps the ATV traffic from having to go along the road. It will so they'll just cross it perpendicularly in that same area that's it's.
[47:06] Chris McDonald: Probably worth noting too as far as the sidewalks and tip downs is that there's there's the trail that's that comes out right there, but there's also an existing gravel road that kind of creates a little triangle there. So the sidewalk will still respect that, so the sidewalk tip downs will be on the other side of that gravel drive, so the gravel drive and the trail will still have access through there. Looks like.
[47:33] Mark Waltz: There's a question in the text, does the current plan take into account bicyclists who may be traveling on Tedford Road?
[47:43] Chris McDonald: And I believe we've already answered that question earlier, but unfortunately given the narrow width of the right-of-way and the need for 11-foot lanes and a sidewalk, we just don't have available right away to be able to include dedicated bike lanes, but.
[48:01] Mark Waltz: Sheroes are a possibility, right? Sheroes, you know the sergeants? Oh right, I think that's.
[48:08] Chris McDonald: Yeah, that I think that could be something that could be incorporated into it, but it would certainly be a shared plane rather than a dedicated lifetime. And there's also, I think we talked this
[48:18] Mark Waltz: two years ago, that if someone wanted, if child's riding a bike in the sidewalk, the police department
[48:22] Public commenter: isn't going to have a problem with that. We're not going to have a problem, so they're allowed lot of a lot of it on the sidewalk. Yes, Brian Benton, bicycle pedestrian committee. I had two really good questions. One is about the long-term traffic plan.
[48:40] Mark Waltz: Mark, you talked about that a little bit. If you could just maybe say a little bit more about the
[48:45] Public commenter: long-term traffic plan, and then the second question is regarding current traffic volumes on the road. Do current traffic volumes necessitate two 11 foot lanes? Let's think that's the second question.
[49:01] Mark Waltz: So for the first one, what I've talked about is pieces that could be put together, you know, hopefully to eventually get this connection that goes from the schools out to Middlesex Road using Tedford Road, K Am Village Drive. At this point the Audubon piece is just that back, you know, it's just an idea. Hopefully we can make that one the one. It certainly isn't going to happen until such time as Highland Green decides to build their memory care facility and upgrade Audubon in the Can-Am. It's still a private piece of Can-Am between the top of the Ararat Hill in Republic. It isn't public, so I can't tell you what date any of this would come to fruition because it's things we'd like to make happen, but there's nothing in place. I'll I'll let you guys answer the second part about traffic. So we're part of that plan dealing
[49:54] Public commenter: when all that comes to pass to round school buses Etc through that route, is that the idea?
[50:01] Mark Waltz: I doubt the schools would ever want, you know, other than maybe a school bus to go to Tedford Road, if that all came to pass. They might decide to do that, but all the buses that they've got right now going up K and M and down Village Drive to take advantage of the lights to get on 201 to go to Harpswell or something, I'm sure they wouldn't want to bring those up out of one. There wouldn't be a reason to.
[50:24] Chris McDonald: Your second question was about lane width compared to traffic
[50:28] Public commenter: volume. So yeah, I'm wondering if the current traffic volume necessitates two 11 foot lanes.
[50:36] Chris McDonald: Yes, well, so the 11 foot lanes that we're proposing here actually mimic the existing conditions on Tedford Road, so that's about, that's about what we have right now is about a 22 foot wide road, so what we're trying to do is replicate those conditions and not make things and try to at least maintain the same amount of traffic, conditions that we would
[51:00] Public commenter: have out there today, and this would have a, this would have a yellow center line, yes, that would, yes, so for example in on Green Street topsum we have a lane or excuse me an old road similar width with no center line and we've got a painted sidewalk slash bike lane on one side, I'm wondering if something like that, do you need a center line, could you buy yourself some space on the sides by getting rid of the center and then maybe you don't need the sidewalk because vice the traffic volume on the road currently is fairly low by road standards, could you get away without doing the sidewalk and having an at-grade facility for both bicyclists and best rates, well it's a good
[51:59] Paul James: but there's enough foot traffic on that road right now that you do need a sidewalk, and we need a sidewalk, people with carriages and kids, yeah, we don't have to down that road and get off the road in someone's lawn to protect themselves, we really need that sidewalk, the
[52:20] Mary Beth (Bike Path Committee): traffic's going on the opposite side of the road to get away from us when we're trying to walk
[52:27] Public commenter: on Green Street is far from the safe street to the office, right, just leave a space that's
[52:33] Paul James: not a good situation originally in the sidewalk but from the other side of the road that bank
[52:38] Mark Waltz: just came in, maybe we'll do a quick survey, raise your hand if you're in the room and you live on [street] or one of the roads off of it, put your hand down if you would rather not have a sidewalk, oh, if you'd rather not have a sidewalk put your hand down, if you want to keep it, if you live on [street] or you want a sidewalk keep your hand up, and then if you live on next question, but my general sense is that people that live on the road want a sidewalk, next question again, put your hand up if you live on [street], raise your hand if you would rather have a road without a yellow center line, I'm sorry, put your hand down if you'd rather have a road without a yellow center line, all right, so for my informal survey it appears of the Tedford Road residents here tonight is the general consensus that people would like the sidewalk and they would like a yellow centerline, yeah, what if you fall on that
[53:57] Josh Jennison: Just in case any of you are wondering about your daily traffic, we've done three studies in the last year out there for traffic and speed, and you average, well, we did one last November, you averaged 901 cars a day out there. We did another week in March and it was 883 cars daily, and then we did one in July, it was 968. So you're just under a thousand cars. I'm sorry, what? Well, we didn't, so when we do the surveys like this, we're putting boxes out there that they don't stand out, they just, let me explain. This real quick, in the past before we had these traffic survey boxes, we used to put the trailer out there, the big trailer that has the sign that tells people what their speed is. Now the problem with that is, I don't think, and it kind of proved, we don't get accurate numbers with that because somebody pulls onto the road, they see the sign and everybody slows down. So since in the last two years, well last fall, we bought these small white innocuous boxes that don't even really notice, they don't get noticed by people. We can put them up on a pole and it just sits there and counts traffic and counts speed. So we've been using those for the last year in town. So it gives us a better idea of what the average traffic is going on the road. So if you'd like to know, I can tell you real quick. We've done three studies. 85% of the cars last November were going 34 or less. We did a study in March. 85% of the cars were going 34 or less. We did one in July. They were going 33 or less. Half the cars. They were all speeding because it's 25.
[55:46] Mary Beth (Bike Path Committee): I'm sorry? They were all speeding because it's 25.
[55:49] Public commenter: 135, I've called multiple times because people are just flying down the road. I feel like there's more control there. I've offered for police to sit my driveway, by all means, yeah, we've done 11
[56:01] Josh Jennison: studies, we've, we've done 11 enforcement details out there, and when we're out there, we're not getting, we're not getting the speeders that 135 type of road. I have a fence, so just sit
[56:13] Public commenter: right there, guarantee you'll get a lot of people. Well, I'll tell you, to be perfectly honest, we
[56:20] Josh Jennison: generally don't run, I mean, yes, one or two or five miles an hour is speeding, but we don't write
[56:26] Glenn Thurston: people summonses for that, right, but they must make sure around because you haven't caught the
[56:31] Josh Jennison: Yeah, no, I mean the simple fact is the people are warning each other when we're out there. 'S only so much we can do. We put the boxes out there that show you know 85 are going nine over or less, but when we go out there nobody's doing it. Two years ago when we had this meeting there was quite a bit of comment about speeding. We spent seven hours over the next two months out there. We got a car at 34, we got a car at 35, one at 38, 37. So the simple fact is we're going out there, but you know people give each other lights. We don't, we're not getting it while we're out there. 'S only so much we can do. I hear you, that's one reason why I was asking about the trees
[57:16] Glenn Thurston: in front of my house and that chain-link fence, because I understand that was, those trees were planted and the fence was put there when a car came out of the old Rusties probably sideways place and hit the house. I
[57:36] Josh Jennison: mean I hear what people say. Again, we're getting, most of the cars are nine over or less, and when we go out there we're not getting them. So yeah, you know, we, you gotta hide though. Well, you know, people always tell us that the problem is the science of radar. We need to have a straight shot to get, and we can't be up somebody's driveway and have a cargo
[57:59] Public commenter: go by and get it. 'S just the radar doesn't work. You can come sleep on my mailbox, because every time I go to get my mail there's people going down the road at least four. You could be going
[58:07] Josh Jennison: to the cul-de-sac. Yeah, and again, when we go out we're not getting it. Everybody's warning each
[58:14] Public commenter: other, and I'm sure that's the information along cops are sitting out there so they
[58:18] Mary Beth (Bike Path Committee): stand down. You can use my car, you can sit in my car with your reader. Other questions?
[58:27] Public commenter: Yes, for years and years we've been talking about connecting to the Highlands from the end of the Petroglyph, and they brought down the sewer, now they brought down the water and drained the palm and everything else, so they're all set up that way. Do you have any, you know, future prediction when that is going to be connected? I know there was a process, this was going on, but I've been hearing about it 10, 50. That's what I was talking about earlier in the meeting. Yeah.
[58:55] Mark Waltz: But it won't happen until they build that memory care facility. And they, the Highlands is trying to be, or Highland Green I should say, yeah, it's trying to be or wants to be full service. So you could go from independent living to assisted living in this memory care facility. That's what's proposed for Audubon. They've come, they have to come in to keep getting their permits renewed because it's all been permitted, but then they don't build it. So they got to come in, it's six months or a year to get permits renewed. They've been doing that for years. So at this point there's no firm date when they would build that facility. So there's no firm date when they would
[59:33] Public commenter: finish out of bond. Okay, you
[59:37] Glenn Thurston: know that particular subject was talked about back when they put the big neighborhood down there, yeah. Because and that became evident this past week, they had a head-on collision down by Rusty's and all the traffic had to go through either Rusty's yard or make
[59:55] Mark Waltz: their way through the accident scene. Yeah, they've been, when we've needed them, you know, to help us out with the connection, they've been willing. As I mentioned when we did the covert work, and I know they would work with us on the railroad piece, but the town doesn't want to build that road, you know. So we're basically waiting for them to do their memory care facility, then they would build it to town specs, and then we could accept it. All right, I
[1:00:21] Mary Beth (Bike Path Committee): have a question. I'm sorry for being
[1:00:23] Public commenter: late. Earlier question, could you speak to the timeline wise, like is this a five year down the
[1:00:29] Mary Beth (Bike Path Committee): road, is this like we're starting July of next year? Again, my apologies for being late, if this was. No worries.
[1:00:35] Mark Waltz: It's all going to depend on the final budget numbers that come in and then planning as the budget goes through this spring. But the hope is to have it summer of 2028 would be the project. Sorry, 27. I'm getting my years confused. Fiscal year 28, which is...
[1:00:50] Mary Beth (Bike Path Committee): How long do you estimate it would take to do the project?
[1:00:57] Chris McDonald: It's a good question.
[1:00:59] Steve Blake: It would be most of the summer.
[1:01:00] Chris McDonald: Yeah, I would say so, like, you know, probably three, four months.
[1:01:08] Mark Waltz: Other questions, any
[1:01:13] Paul James: more online or no? I have one more. When the past road commissioner was here, he told me that we could still keep our mailboxes on our side of the road, and I'm wondering what changed that. Postmaster, the
[1:01:36] Mark Waltz: Brunswick postmaster is in charge of all the world delivered, and when these guys contacted him, he said they'd be fine with the mailbox, but they'll have to be moved to the side of the road. Correct.
[1:01:46] Paul James: He said that we he had a place where he's doing it right now, that they had some place where the mail doctors were stayed on the sidewalk side, so he says Paul you won't have a problem and still
[1:02:01] Mark Waltz: The mailbox on your side of the road. I think what's happened is you've all seen the stories on TV about people aren't getting their mail or the post office can't find enough workers, and so I think they're using this as an opportunity to try to make their mail more efficient on Tedford Road because it's certainly easier for them to deliver all the mail on one side of the
[1:02:21] Paul James: Street. So that doesn't make sense to me because they've got to come back down on the road, so as many stops as they have they're going to have that same amount. Yeah, but now there's two directions now
[1:02:32] Steve Blake: They have to sidewalk in a way so they can't they have that they have that gap between the road
[1:02:38] Paul James: Yeah, well they told me it could be done with the sidewalk and my mailbox could still be on the edge of the road. Yeah, they changed that
[1:02:50] Mark Waltz: Because believe me we'd rather not move if we didn't have to because it costs us more money
[1:02:54] Public commenter: To move the mailboxes there's a there's a method through the postal service where you can put it in a hardship and you can try to get them forced to hand deliver your medicine. If you have an issue, if you make it, I'm just letting you know that any other questions.
[1:03:10] Mark Waltz: If no other questions, what we'll do is we'll stop the recorded portion, large group portion of the meeting and you're free to look at any of the drawings and if you have particular trees, you want to call to these guys attention feel free to do that or any other issues you want to call their attention. Mentioned and we'll move on to that now we brought a bunch of cookies too so please